City of Richmond (CoR) Miller/Wellington Alleyway Upgrade Project 2026: Project Completion (early September)
July 29th, 2026
Update from Roger Keating (CoR)
(Week of July 27-31, 2026)
Project Completion (early September)
The Miller Road Laneway [upgrade] is nearing completion.
All underground pipe work should be completed this week. [July 27th]
New drainage storm sewer pipe was installed in the laneway along with replacement of the old sanitary sewer system.
Grading of the back lane will be completed next week [August 3rd], with paving of the laneway [will be] scheduled for mid to late August
Followed by shouldering and clean up.
All works should be completed by the first week of September.
…