City of Richmond (CoR) Miller/Wellington Alleyway Upgrade Project 2026: Project Completion (early September)

July 29th, 2026

Update from Roger Keating (CoR)

(Week of July 27-31, 2026)

Project Completion (early September)

The Miller Road Laneway [upgrade] is nearing completion.

  • All underground pipe work should be completed this week. [July 27th]

  • New drainage storm sewer pipe was installed in the laneway along with replacement of the old sanitary sewer system.

  • Grading of the back lane will be completed next week [August 3rd], with paving of the laneway [will be] scheduled for mid to late August

  • Followed by shouldering and clean up.

All works should be completed by the first week of September.

For more information please feel free to contact either our

SICA Community Development Committee: CommunityDevelopment@sea-island.ca

OR:

Roger Keating (CoR Project Manager): RKeating@richmond.ca

Sea Island Community Association

Sea Island Community Association
Richmond BC V7B 1H7

https://sea-island.ca
Previous
Previous

City of Richmond (CoR) Stirling/Hudson Alleyway Upgrade Project 2026: Project Start (late August)

Next
Next

City of Richmond (CoR) Miller/Wellington Alleyway Upgrade Project 2026: New Curb Lane Parking Bypass