City of Richmond (CoR) Miller/Wellington Alleyway Upgrade Project 2026: Project Completion (early September)

July 29th, 2026

Update from Roger Keating (CoR)

(Week of July 27-31, 2026)

Project Completion (early September)

The Miller Road Laneway [upgrade] is nearing completion.

  • All underground pipe work should be completed this week. [July 27th]

  • New drainage storm sewer pipe was installed in the laneway along with replacement of the old sanitary sewer system.

  • Grading of the back lane will be completed next week [August 3rd], with paving of the laneway [will be] scheduled for mid to late August

  • Followed by shouldering and clean up.

All works should be completed by the first week of September.

…

For more information please feel free to contact either our

SICA Community Development Committee: CommunityDevelopment@sea-island.ca

OR:

Roger Keating (CoR Project Manager): RKeating@richmond.ca

…

Sea Island Community Association

Sea Island Community Association
Richmond BC V7B 1H7

https://sea-island.ca
Previous
Previous

City of Richmond (CoR) Stirling/Hudson Alleyway Upgrade Project 2026: Project Start (late August)

Next
Next

City of Richmond (CoR) Miller/Wellington Alleyway Upgrade Project 2026: New Curb Lane Parking Bypass